Thank you for reporting! A work order has been created for this issue. Staff will be scheduled to investigate this issue. We will keep you updated on our action.
What happened to the project where we were going to have five minute drop off and to restructure the parking lot for flow through. Here’s the traffic engineers response for issue 4522251?
CLOSED David Y., Traffic Engineer (Verified Official)
The work for the 5 minute drop off parking should be completed by mid july
06/19/2018 · Flag
Thanks for using SeeClickFix! Staff have resolved this issue. If you have any questions or concerns regarding this issue, please call the Maintenance Division at (707) 648-5235. Thanks again for using SeeClickFix!
7 评论s
Coco (注册用户)
已确认 Public Works Maintenance Worker I (官方验证)
For a better Vallejo (注册用户)
Artsem (注册用户)
What happened to the project where we were going to have five minute drop off and to restructure the parking lot for flow through. Here’s the traffic engineers response for issue 4522251?
CLOSED David Y., Traffic Engineer (Verified Official)
The work for the 5 minute drop off parking should be completed by mid july
06/19/2018 · Flag
For a better Vallejo (注册用户)
关闭 Public Works Maintenance Worker I (官方验证)
Artsem (注册用户)